Concrete Calculator

A 20 × 15 ft slab at 4 inches thick needs 3.70 cubic yards of concrete, so order 4.07 yards. Pick slab, wall or round pier, enter the size, and the calculator works out cubic yards and cubic feet, the number of 80, 60 and 50 lb bags, the truckloads and the cost of ready-mix versus bags.

Key facts:
  • Cubic yards = length × width × thickness (all in feet) ÷ 27.
  • One cubic yard takes 45 bags of 80 lb, 60 bags of 60 lb or 72 bags of 50 lb.
  • Always order 10% extra for uneven ground and spillage.
  • A 20 × 15 ft slab at 4 in needs 4.07 cubic yards to order.
  • Ready-mix is usually cheaper than bags once the job passes about 1 cubic yard.

How this tool differs: This is the general concrete calculator: slab, wall and pier modes with bags, trucks and cost in one place. The other concrete pages do one job each — price comparison, formulas, square feet, yards only, triangles, bags only, footings or foundations.

Loading calculator…

Share or Export Current Results

Share Concrete Calculator directly or copy link to clipboard

TwitterLinkedInFacebookWhatsApp

Calculation Formula & Mathematical Engine

Theoretical equation governing this computation.

CuYd = \frac{L \times W \times T}{27}, \quad Order = Net \times (1 + Waste\%), \quad Bags_{80} = \frac{OrderCuFt}{0.6}

Variable Definitions

L, W, TLength, width and thickness — all converted to feet before multiplying
CuYdCubic yards — the unit ready-mix suppliers sell by (1 cu yd = 27 cu ft)
Waste\%Waste buffer for uneven ground and spillage — 10% is standard, 15% for rough excavation
Bags_{80}Number of 80-lb bags, rounded up (one 80-lb bag makes 0.60 cu ft)

Step-by-Step Calculation Example

Concrete for a 20 × 15 Ft Slab at 4 Inches Thick

Scenario: A homeowner pours a 20 ft by 15 ft patio slab, 4 inches thick, and wants to know how much to order and whether bags or a truck are cheaper.
Slab Size20 ft × 15 ft, 4 in thick
Waste Buffer10%
Prices$150 per cu yd ready-mix, $5.50 per 80-lb bag
Execution Steps
  1. 1Net volume: 20 × 15 × (4 ÷ 12) = 100 cubic feet
  2. 2Cubic yards: 100 ÷ 27 = 3.70 cubic yards
  3. 3Order with 10% waste: 100 × 1.10 = 110 cubic feet, or 4.07 cubic yards
  4. 4Bags: 110 ÷ 0.6 = 183.3, so 184 bags of 80 lb (245 of 60 lb, 294 of 50 lb)
  5. 5Trucks: 4.07 ÷ 10 = 1 truckload
  6. 6Cost: ready-mix 4.07 × $150 = $611.11; bags 184 × $5.50 = $1,012.00 — ready-mix saves $400.89
Final Verified Output:4.07 cu yd to Order | 184 Bags (80 lb) | 1 Truck | Ready-Mix $611.11

How to work out how much concrete you need

Follow these steps to get your result.

  1. 1Pick the project type: slab, wall or round pier.
  2. 2Measure the length, width and thickness in feet and inches.
  3. 3Enter the size to get the net volume in cubic yards and cubic feet.
  4. 4Read the order volume with the 10% waste buffer, the bag count and the truckloads.
  5. 5Compare the ready-mix cost with the bag cost and order the cheaper one.

Comprehensive Practical Guide

In-depth analysis, domain guidelines, standard practices, and common pitfalls.

How Much Concrete Do I Need for a Slab?

Multiply length × width × thickness with all dimensions in feet, then divide by 27 to get cubic yards. A 20 × 15 ft slab at 4 inches is 100 cubic feet, or 3.70 cubic yards. One cubic yard covers 81 sq ft at 4 inches thick, 65 sq ft at 5 inches and 54 sq ft at 6 inches — so you can also work backwards from the area. Always add a 10% waste buffer before you order.

Bags or Ready-Mix: Which Is Cheaper?

Bags win on small jobs and trucks win on big ones. One cubic yard takes 45 bags of 80 lb, so a job under about 1 cubic yard is usually cheaper in bags — no delivery fee, no minimum load, and you mix only what you need. Above about 1 cubic yard the truck is almost always cheaper: the worked example above costs $611.11 by truck against $1,012.00 in bags. Watch for short-load fees on small ready-mix orders, usually under 2–3 cubic yards.

Why Order 10% Extra Concrete?

Three things use more concrete than the drawings say: uneven subgrade (the ground is never perfectly flat), spillage and form movement, and over-excavation where the digger went too deep. Ten percent covers normal formed work on compacted base; use 15% when pouring against rough excavation with no forms. Running short mid-pour is far worse than a small leftover — a cold joint between two pours is a weak line in the slab.

Frequently Asked Questions About Concrete Calculator

Direct, verified answers to common calculation and methodology questions.

About 1.23 cubic yards net — order 1.36 yards with a 10% buffer. That is 62 bags of 80-lb mix with the buffer, or 56 bags without it.
Authoritative Sources & Data References:
  • National Ready Mixed Concrete Association (NRMCA) — Ordering Ready Mixed Concrete
  • American Concrete Institute (ACI 318 — Building Code Requirements)
  • Method: volume = L × W × T ÷ 27; bags use manufacturer yields of 0.60 / 0.45 / 0.375 cu ft per 80 / 60 / 50 lb bag; costs use example rates of $150 per cu yd and $5.50 per 80-lb bag.

Disclaimer: Prices are examples — check your local supplier for current ready-mix and bag prices. This tool estimates volume; structural slabs and footings must follow local building codes.